Case study 11LondonAluminium cladding

Royal Victoria

Aluminium cladding & copings

Client
City & Docklands Property Group
Address
Docklands, London E16 1YN
Our role
Specialist installation contractor
Disciplines
Aluminium cladding, Copings
Package value
c. £150k
Programme
4 months
Team
6 OMFC operatives in two teams
Completed
2018

The outcome

Two teams working in parallel completed the facade cladding and roof copings in four months.

The two curved residential towers from street level.
The two curved residential towers from street level.

Overview

For City & Docklands Property Group, OMFC delivered the aluminium facade cladding package at Royal Victoria, completing the works in four months.

A four-person team installed the aluminium cladding to the facades, while a second two-person team worked at roof level to complete the aluminium copings. Running the two teams in parallel kept the package on a tight programme.

Scope of works

  1. Aluminium facade cladding
  2. Aluminium copings at roof level
  3. Six OMFC operatives across two parallel teams
  4. Completed in 4 months
Next case study 12 / 17 Crossways Commercial Park